Scheduling control



The examination procedure takes, on average, 10 to 12 months between the date the completed and compliant application is submitted and the date the prefectural order is signed.
This should be taken into consideration when establishing the provisional start-up schedule of your installation.

The Inspectorate of classified installations is striving to control this examination time as part of its modernisation and reinforcement programme stipulating that, in the long term, 95% of permit applications for new projects should be examined within one year.